Construction Schedule
2010
  Aug. 15 Materials begin to be removed from Noble
     
  Oct. 1 Noble Closes to the Public
  Oct. 4 After-school program starts at Noble
  Oct. 5 All Materials moved out of Noble
  Oct. 6 Computers moved out of Noble
  Oct. 11 Surplus Sale
Oct. 12 Construction bids are due to Lee Road, public opening 2:00 pm
  Oct. 19 Library Board Meeting to award contracts
  Oct. 25 Asbestos abatement begins
     
  Nov. 30 Asbestos abatement completed
 

Dec. 15 Demolition Begins
Late Dec. Construction Begins
2011
  Apr. 15 Construction Complete
Apr. 25 Library Materials Stocked
 
May 12 Friends Fundraiser
May 15 Open House for the public
May 23
Open for business at 1:00 pm

2011 - Phase 2
  Jul. 6 Bidding for plumbing opens
  Jul 13. Walkthrough at Noble Library
     
  Aug. 3 Bidding closes with open reading of bids at 2:00 pm at the Lee Road Library